20.05.2022 – good vibrations

the vibration test systems arrive

On 16.05.2022, the mobile lifting device for the installation of our two shakers from TIRA GmbH arrived. The premises of our Battery Test Centre LABCO BTC were extensively prepared so that the systems could be set up on the same day (Images 1 – 4).

Over the next few days, the individual components of the vibration test systems were delivered and installed day by day, one after the other and with the utmost care (video will follow). The electrodynamic vibration test equipment will be able to test with a nominal force of up to 300 kN (sine/noise) and 900 kN (shock), so it comes as little surprise that the heaviest component weighs over 15 t! (Images 5 – 8)

Image 9 shows the current state of the battery test systems. However, a few individual components are still missing, because our vibration test systems should not “only” be able to vibrate batteries, but also test them under a wide range of thermal environmental profiles.

We will present the completely finished systems to you soon. Stay up to date with and through us. You can find more information about our “shakers” with temperature chamber here.

26.04.2022 – soar

The upper floor

The offices for the staff have already been built out so that work on the upper floor can continue. In the images 1 – 3, the structures of the office rooms can be clearly seen. Here, the future employees of our Battery Test Centre LABCO BTC will become members of our teams in a comfortable working atmosphere. By the way: We are still looking for employees for LABCO and LABCO BTC. Interested parties are welcome to visit our homepage to find out about our advertised vacancies. We also welcome unsolicited applications.

https://labco.de/unternehmen/karriere.html

While the images 4 – 5 show the (almost) finished roof installations of the upper floor, there is just as much going on “in the background”: All building services are already being installed. This means that the sanitary facilities, the ventilation and the electrical systems are being installed.

For an overall view of our new building, however, we would like to accompany you up the stairs in a short video. Enjoy the view!

14.04.2022 – keeping track of everything

Easter’s coming

Our latest images show that now not only our room for our future vibration test systems is completely shining in LABCO colours, but also that the first steps for finished entrances are created. After all, we want to open our doors for you in the fall of 2022. With this construction progress of our future Battery Test Centre LABCO BTC, we are happy to go into the Easter holidays.

We wish you a happy Easter and of course spring-like weather!

25.03.2022 – we show our true blue colors

First coat of (LABCO-blue) paint

Cooperate Design plays an important role for us. In this context, logo and colour communication is essential for our Cooperate Identity, so it can project who we are, both internally and externally.

In the images you can follow the development of our room for the future vibration test systems. The smoothly concreted and well-prepared room has now received its first coat of paint in LABCO blue – we will of course publish the final result.

11.03.2022 – The laboratory from the inside

first impressions

The progress since 23.02.2022 is remarkable: The ceiling has been poured and smoothed, the walls have been put up and are now being plastered.

Today we took the first pictures of the interior. Image 6 shows the laboratory rooms. On the right side will be our climatic test system, on the left our battery test systems. On Image 7 and 8 you can see the pits of our future vibration test systems. The rails for the vibration temperature test chamber are also already attached to the ceiling and walls.

We are impressed by the dimensions of the rooms and it is getting easier to get an idea of the laboratories of our future Battery Test Centre.

22.02.2022 – Storm front and flooding

Ylenia, Zeynep & Antonia

Our construction site before and after the storm: images 1 – 2 were taken on 10.02.2022, images 3 – 4 on 18.02.2022 and image 5 today. We are glad that we have largely managed the storm front last week without any great damage, which is not a matter of course.

Thanks to the employees of our construction site partners, everything was quickly put back in order and the construction work of our Battery Test Centre LABCO BTC could continue.

This is not a creek…

04.02.2022- ‘The time to repair built the roof is when the sun is shining.’

(John F. Kennedy)

The construction work on the roof scaffolding of our soon-to-be-standing building has begun.

In addition, the first structures of special building constructions for our future device park can already be seen, such as the pit for our electrodynamic shakers (picture 2 and 3).

January 2022 – IT’S GOING FORWARD

THE PROGRESS OF CONSTRUCTION SINCE LAST YEAR

Since the start of the ground works, you can observe almost daily how the building complex on our site is taking more and more shape…

September 2021 – ground workS

It happened so quickly

At the beginning of last week, there was still green field and already on Friday, the company Erich Thiess & Sohn GmbH took the first visible steps towards the LABCO BTC building with excavation work for us.

We are looking forward to the next steps.

10.09.2021 – Groundbreaking

The first step IS MADE

Yesterday we were visited by the Nordsee-Zeitung, the WESER-KURIER, representatives of the municipality of Loxstedt and representatives of the Agency for Economic Development Cuxhaven to celebrate the symbolic ground-breaking ceremony of our sister company LABCO BTC.